The crane operator should carry out a visual inspection and functional test before the commencement of each work shift, including inspecting and testing the following:
- all relevant items indicated in the operations manual;
- operating and emergency controls;
- brakes;
- safety switches and interlocks, including limiting and indicating devices;
- visual inspection of the structure; and
- wire ropes to ensure they are on the drum and correctly reeved on the sheave.
The results of the inspection must be entered into a logbook and kept with the crane.
All personal protective equipment should also be inspected to ensure it is functioning correctly. All safety-related problems must be corrected before the crane is used, and recorded at an appropriate time.